Economic Governance Reform Programme I (EGRP I)

PN10323 | Project Completion Report Review Note | 15-Jun-2011





Download Report
Lesson(s)
 
3) Budget support aimed at strengthening PFM reforms continue to be a valid instrument for engagement in Sierra Leone. The EGRP I in combination with an ISP have helped strengthen budget execution, reinforce external scrutiny, and improve debt policy


Recommendation(s)
 
2) Recipient(s): Bank : Coordination between the field office and Tunis should improve

3) Recipient(s): Bank : Supervision, reporting and hand-over arrangements need to be strengthened

4) Recipient(s): Bank : The Bank could strengthen its role in the MDBSG by taking on more vocal and proactive role in coordinating PAF, defining priority areas for reform and providing support in areas where it can provide strong expertise


Ratings

Countrie(s):
Sierra Leone
Sector(s):
Multi-Sector
Project(s)
P-SL-KA0-010




Attachment(s)  
Summary Report PN10323_SR_EN PN10323_SR_EN.pdf