Airport rehabilitation project

PN10008 | Project Completion Report Review Note | 26-Apr-2004





Download Report
Lesson(s)
 
1) In the procurement of electric or electronic equipment, it is important to avoid giving highly detailed specifications since the sector is evolving so rapidly. For example, certain parts and brands are no longer produced and those available are inefficient. This situation was one of the causes of the major delay in project implementation.

2) Preparation and appraisal teams for such projects, which tend to be highly specialized, should always include as many specialists as possible. This would enhance the identification of constraints and help avoid any errors of judgment.



Ratings

Countrie(s):
Morocco
Sector(s):
Transport
Project(s)
P-MA-DA0-001